Temporary emergency power at H. Essers: fast response for a secure data centre

At the H. Essers site in Genk, the data centre’s emergency generator failed unexpectedly — and in a data centre, every second counts. Without backup power, operations and data integrity are immediately at risk. Boldt responded quickly and installed a temporary standby generator configured to start automatically in the event of a power outage. The existing UPS system absorbed the initial load, while the temporary generator remained on standby to ensure maximum continuity. As a result, all systems stayed fully operational — with no data loss, no downtime and no compromise to security. This temporary setup provided a safe bridge until the permanent installation was restored.
PAST PROJECTS
  • Installed a temporary emergency generator with automatic start-up in case of grid failure
  • Provided a full backup solution after the existing emergency generator malfunctioned
  • Ensured seamless integration with the existing UPS system for uninterrupted power transfer
  • Executed a rapid on-site intervention at a critical data centre location

Curious to discover our ideas about your project?

Request a consultation

Dirk Koopmans

Director

dirk@boldt.tech